Contract #7 - Gurley Road Backup Well

On November 13, 2018, EFRW gave Griner Drilling Notice to Proceed with the drilling of the backup well at the Gurley site which is an existing well site on Hwy 68 just south of Wilson.  This new well will serve as a backup for the existing Gurley distribution system which services nearly 1200 customers from the middle of the parish and westward .  In October 2019, the new well passed all LDH bacteriological sampling and was placed into active service while the old well was taken off line for repairs and maintenance. 

Contract #1 - Phase 1 Line Improvements

On October 18, 2019, EFRW gave Greenbrier Digging Service  Drilling Notice to Proceed with line improvements on Sam Talbert and Hwy 68.  Greenbrier has scheduled to begin work on October 28th.  Crews are expected to begin works in the Sam Talbert area. While every effort will be made to ensure your services are not interrupted, we ask that you prepare for outages, boil advisories, and brown water by having an emergency supply of water on hand.  We will issue boil advisories as necessary to ensure the safety of your drinking water.  We appreciate your patience and your consideration of these crews working in the area.

Contract #1 - Phase 1 Line Improvements

Update as of December 11, 2019


As of today, Greenbrier is almost complete with the laying of approximately 4 miles of 8" water main in the Sam-Talbert Road area.  Crews are currently performing directional boring in order to make some tie ins.  EFRW residences did experience some extremely brown water issues the past several days.  This issue affected a portion of EFRW's service area that we had not foreseen any impact from the on going construction.  This incident was due to the use of a fire hydrant at the end of Senat Lane.  The contractor has been instructed to utilize a fire hydrant in another location to lessen the impact on our neighborhoods.  EFRW apologizes to those that were caught off guard and inconvenienced.  A portion of the system upgrade includes flush valves.  Once these valve are installed EFRW will be able to clean out lines and initiate a maintenance flushing program.


After the first of the year, some areas  will be contacted regarding scheduled outages as EFRW isolates the system in order to install valves on existing water mains.  More information will be provided at that time.  


Contract #7 - Gurley Road Backup Well

Updated as of December 11, 2019

The new well, Gurley #2, is online and supplying water to customers.  The old well, Gurley #1, has been taken out of service for repairs and maintenance.  Work at the well site is wrapping up with finishing touches to the chlorination, and electrical systems.  Once everything is tied back in Gurley #1 and Gurley #2 will be alternating water supply to customers.

              Line Improvements 9-09-20

 Greenbrier has scheduled to begin line work on Dawson road.   While every effort will be made to ensure your services are not interrupted, we ask that you prepare for outages, boil advisories, and brown water by having an emergency supply of water on hand.  We will issue boil advisories as necessary to ensure the safety of your drinking water.  We appreciate your patience and your consideration of these crews working in the area.